Answer: Fixed price for a fixed amount of work Explanation: Our pricing depends on many variables,
-Size of the project
-Standard or Custom
-Time of the project
-How many employees, (labor)
-What trades will be on site, (electrical, plumbing, masonry, exteriors, and more)
-Type of materials to be used
-Filing fees, (only if required)
-Business taxes
-Office administration
-Length of the Scope of Work Contract for Residential or Commercial work
Any type of delays, (weather, deliveries, change orders, permits and more) |
| I've Got Properties 4 U LLC |
Answer: Price not to exceed (NTE) Explanation: Price not to exceed is very common. We are flexible depending on the project, as we believe most contractors should be (but are not) |
| Mercury Builders |
Answer: Fixed price for a fixed amount of work Explanation: The most common way contractors bid on projects is by offering a fixed price for a clearly defined scope of work. This means the contractor provides one total price to complete the entire project as agreed, giving clients a clear understanding of costs upfront and helping avoid unexpected expenses. |
| Valley Vista Construction LLC |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: A fixed-price bid, also called a lump-sum bid, sets a specific amount the contractor will be paid to complete the defined scope of work. This approach is popular because it gives the client certainty about the total project cost and allows the contractor to plan and manage resources efficiently. Time and materials (T&M) or price-not-to-exceed (NTE) bids are used in more flexible or uncertain projects, but fixed-price bids dominate most standard construction and landscaping contracts. |
| Linares Landscaping Services LLC |
Answer: Fixed price for a fixed amount of work Explanation: This is a safe way to protect the homeowner and ensure they have the proper funds prepared to pay for the services needed. T&M and NTE serve a purpose with repairs or challenging immediate issues to allow work to be started, but planning phase we advocate for a fixed contract with language for unforeseen acknowledgement. |
| Total Roofing and Construction |
Answer: Fixed price for a fixed amount of work Explanation: we give you multiple choices and options to choose from with regards to insulation for your home. We also offer financing as a service if you’re paying cash, we do require half upfront at the siding of the sales agreement and the other half when the job is completed. |
| LAT solutions |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Time and Materials (T&M) is a contract structure where the client pays for the actual cost of labor, materials, and other expenses.
|
| Remo Construction |
Answer: Fixed price for a fixed amount of work Explanation: fixed price with detailed description |
| Valley Development Corp |
Answer: Fixed price for a fixed amount of work Explanation: Fixed price for a fixed amount of work means the contractor gives you one set price for the entire project based on an agreed-upon scope of work. The cost doesn’t change unless you request additional work or changes. This option gives homeowners peace of mind because they know the total price upfront, and it allows the contractor to plan materials, labor, and scheduling more efficiently. |
| GOLD Remodeling |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: The contractor agrees to complete the entire project for a single, predetermined price. This price is set before any work begins and generally does not change, regardless of the actual time or materials expended by the contractor. Unless the customer wants to change/add to the project. If so, the customer will agree to a price change before the change/add to the project begins.
|
| HITTMAN handyman services L.L.C. |
Answer: Time and materials (T&M) Explanation: Due to the lack of top tier staff a lot of businesses don't have the man power required to bid fixed price because there will always be unforeseen or if you're like me do it all always some extras that add time and sometimes multiple days to your timeline and not having the bodies to still get the first job done on time while you or the lead has to stop doing their part and tackle this extra usually specialty work. |
| Home Pros |
Answer: Time and materials (T&M) Explanation: We supply skilled construction labor per man per hour allover the USA and overseas |
| MANIT INTERNATIONAL SKILLED LABOR SERVICE |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: Fair and reasonable - generally costs plus 15% |
| JMF Construction |
Answer: Time and materials (T&M) Explanation: Due to the economy; materials have exceeded the price of labor, so we remain fair by keeping adjusting labor so that homeowners can afford to pay for their project. |
| H Construction & Management LLC |
Answer: Time and materials (T&M) Explanation: Most of the paint contractors I know bid by time and materials. I prefer to be more consistent and find sq. ft bidding for paint services works pretty well, but I offer a lot more than paint services and it’s not always so cut and dry so sometimes I have to just go old school and bid by time and material. |
| Apache Restoration and Design |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: Giving customers a fixed price helps them to budget there projects.
We also offer options for our customers so they can reach there goals often times in phases . |
| Pioneer engineering and construction |
Answer: Time and materials (T&M) Explanation: We provide estimates: we bid material and labor costs at a fair rate |
| Texas Made Renovations LLC |
Answer: Fixed price for a fixed amount of work Explanation: We price custom to what the customer needs. We do a meet and greet, take pictures and pull measurements, and get a bid turnkey with selections allowances. |
| TEAM TRIM ENTERPRISES LLC. |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Time and materials how long to do it and how much it's going to cost |
| We Mean Business |
Answer: Time and materials (T&M) Explanation: This ensures that both parties get on the same page as to what materials will be used and how long the project will take. |
| RENOvation Revelation |
Answer: Fixed price for a fixed amount of work Explanation: The best way to anser this is to say that there is no one way each job will have a different type of bidding. So you may have a fixed price on one bid and then turn around on another bid and it would be best to to time and material , or a customer might tell you what all they "Eventually" want to get done to something but this is what i have right now so pls dont exceed this amount right now so in my experiance i would have to say All of them could be the most common way... |
| Infinity Custom Concrete & Construction |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: We provide our estimate. We stay on-time & on-budget! |
| Austin Roofing and Construction |
Answer: Time and materials (T&M) Explanation: Contractors use the time and materials (T&M) method for bidding on projects for several reasons:
Flexibility: T&M contracts offer flexibility for projects where the scope of work is uncertain or subject to change. Instead of providing a fixed price based on a defined scope, T&M contracts allow for adjustments based on the actual time and materials required as the project progresses.
Transparency: T&M contracts provide transparency to both the contractor and the client regarding the costs associated with the project. Clients can see a breakdown of labor hours, material costs, and other expenses, which helps build trust and understanding between parties.
Complex Projects: For complex projects with variable requirements or unforeseen challenges, T&M contracts can be more appropriate than fixed-price contracts. They allow contractors to adapt to changes and address unexpected issues without renegotiating the entire contract.
Cost Control: While T&M contracts may seem less predictable than fixed-price contracts, contractors can still implement measures to control costs and ensure efficiency. This includes providing detailed estimates, tracking time and materials carefully, and communicating openly with the client about any deviations from the original plan.
Client Involvement: T&M contracts often involve greater client involvement in decision-making and project oversight. Clients have more input into the direction of the project and can make adjustments based on their preferences or budget constraints.
Overall, the T&M method provides a balance of flexibility and transparency, making it suitable for certain types of projects where fixed-price contracts may not be feasible or practical. However, it's essential for both contractors and clients to establish clear expectations and communication channels to ensure the success of T&M projects.
|
| DJ CONSTRUCTION SERVICES OF NEW YORK, LLC |
Answer: Price not to exceed (NTE) Explanation: Normally customers have a cost project budget and my company always is commitment to adjust from our estimate to the customer budget. |
| DeRivera construction |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: A contract between Owner & CIM - Construction In Motion, Inc detailing every step of the scope of work to be performed. With scheduled payment. |
| CIM - Construction In Motion, Inc. |
Answer: Fixed price for a fixed amount of work Explanation: We do smaller jobs for time and materials but larger jobs will be bid based on square footage |
| M&D Home Improvement |
Answer: Time and materials (T&M) Explanation: Time and materials is the most cost effective way to get the right number for your bid. |
| Solid Solutions Concrete LLC |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Time and material is more simple and faster then pouring over pricing all day |
| Majestic Construction & Remodeling |
Answer: Fixed price for a fixed amount of work Explanation: Most projects are done by a fixed bid. Unless it's a service or maintenance repair than it can be a time and material. |
| C.E.M CONSTRUCTION SERVICES |
Answer: Time and materials (T&M) Explanation: Labor and materials or just price for labor with client providing materials. |
| Sunnyskies |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: I will give the home owner my best price and a detailed offer that includes everything the home owner wants in there new bathroom. Plus we always upgrade the fixtures for free !!!!!! |
| American Eagle Construction |
Answer: Fixed price for a fixed amount of work Explanation: Contractors normally charge by the square ft. For residential roofing that number is around $4 - $5 per square ft right now. |
| Partain Roofing LLC |
Answer: Fixed price for a fixed amount of work Explanation: It’s charged by how many yards of concrete in square footage how much 21 AA needs to be brought in compacted, and if we had the buggy, the concrete and how much side or concrete needs to be removed to set forms and grade |
| D&L Concrete LLC |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Time and materials is what we have been doing Jobs for. because of the volatility of cost. We started doing time and materials when our cost increased monthly. On some small projects we can still bid jobs. |
| Elkhorn Mtn Construction LLC |
Answer: Fixed price for a fixed amount of work Explanation: Everything will be listed in the contract between the homeowner and the contractor provided by us and we read through together and explained thoroughly we are completely transparent |
| George Kelley construction |
Answer: Fixed price for a fixed amount of work Explanation: We run a model on pitch X squares = bill |
| Outlaw design and roofing |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: The time is really a close guess that takes years of experience to get right. Materials is always right if you know how to do a take off on a design/blueprint correctly. |
| Navarro design and build |
Answer: Fixed price for a fixed amount of work Explanation: In most cases, contractors can give a set price on a project. Other times, it is very difficult to put a set price due to unforseen items or a large list of small items. |
| Burch Contracting |
Answer: Fixed price for a fixed amount of work Explanation: 4 Square Roofing provides an ariel measurement for each new roofing system replacement with our partners at Eagleview along with a labor and material proposal based upon the current market price per roofing square for remove and replacement. |
| 4 Square Roofing |
|
| ProMatcher |
Answer: Price not to exceed (NTE) Explanation: WE USE NTE ONLY BECAUSE WE DONT WANT TO MAKE YOU GO BROKE WHILE MAKING YOUR DREAMS COME TRUE WE WILL HELP YOU IN ANY WAY POSSIBLE AND STAY WITHIN YOUR BUDGET |
| Flores Concrete & Constructon |
Answer: Time and materials (T&M) Explanation: Estimates are given for labor costs and with customer wants in material cost |
| R&R RENOVATION |
Answer: Fixed price for a fixed amount of work Explanation: I like to come to an agreement on the labor of work for the project |
| Gregs Touch LLC |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Example for an exterior paint job. We would create an itemized quote by doing a walk through of the property that goes over each area being painted, cost of materials and different paints needed to complete the job. Then we will email the customer a quote that breaks down the cost in great detail. |
| Veteran Paint Squad |
Answer: Time and materials (T&M) Explanation: However this is not always the best option for the customer. I personally do fixed price/work, with a sidenote for any possible issues that may arise (this is mainly while doing remodels or fixing someone elses mistakes) after 30+ years in the trades you get good at predicting issues on a project. |
| CLK Drywall & Handyman Svcs |
Answer: Fixed price for a fixed amount of work Explanation: I think the most common way to bid on project used by a majority of contractors is a certain price per sq ft.
I think this is the most accurate way on most projects because it takes the time element out of it. And both the contractor and the homeowner know exactly what they are going to make and what they are going to pay up front. With T&M it could end up costing the client more money. |
| New Horizon Construction and Remodeling LLC |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: FREE ESTIMATES |
| ABATECO |
Answer: Time and materials (T&M) Explanation: Sometimes issues arrive unexpectedly that may cost more but we pride ourselves in coming in under budget as often as possible. |
| AR Construction |
Answer: Fixed price for a fixed amount of work Explanation: On projects that provide plans with set guidelines for the project, we use a fixed price method of bidding so the client knows the cost for their project. |
| Innovative Construction South, LLC |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: We charge by per Job we calculate hours and overhead , and materials. |
| A+ Realty and Construction LLC |
Answer: Fixed price for a fixed amount of work Explanation: Flat Fee based on Construction COST is the most cost efficient way for a consumer. |
| Melissa Anne Construction Services |
Answer: Fixed price for a fixed amount of work Explanation: Clients receive a bid and timeline based on initial review of the project. If no hidden repairs are found during demo or the customer does not change their mind about the finished product, the original bid will be upheld; this will be explained when signing the contract to begin labor. |
| Strock General Contracting LLC |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: Its the only way to compare apples with apples. |
| Thibodeau Contracting, Inc. |
Answer: Time and materials (T&M) Explanation: Many contractors bid based on time and materials as a method to manage projects. This has its place in certain situations. Most often however, an estimate in bid is based upon initial guess of amount of time and materials to complete a given project and typically has a variance factor of plus or minus 10%. The advantages of this are at least relatively close ballpark of what the overall project should cause. Any additions or change orders requiring more labor or materials throughout the project obviously must be renegotiated as what's known as a change order. Change orders are typically agreed upon in writing and signed by both parties and dated and typically are above and beyond the initial scope of work and bid. |
| Premier Construction Services |
Answer: Fixed price for a fixed amount of work Explanation: Contractors will bid the initial job at fixed amount and any extras that may arise can be either a fixed amount, time and material or a cost plus not to exceed. No extra work should be preformed without written consent. |
| Banning Construction Services |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: Sq ft and core surface |
| Saunders Insulation |
Answer: Fixed price for a fixed amount of work Explanation: This way you know what the project will cost |
| landmark builders & excavating LLC |
Answer: Fixed price for a fixed amount of work Explanation: Time, materials, difficulty, and paperwork all add up to a fair and responsible fixed price. |
| Whatdaddywontdo And Gutter Guys |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: We complete hazard claims with a set price. We use a cost estimatation program for bids. |
| HHS serviced |
Answer: Fixed price for a fixed amount of work Explanation: Every job and situation is different , so for the majority of work we do is priced per project with a singed contract , but some jobs cannot be estimated like this so we would go with time & materials |
| Fallston Remodeling & Carpentry Inc |
Answer: Fixed price for a fixed amount of work Explanation: AA Plus Construction.
We do all types of Construction: Residential, or Commercial.
* Roofing . * Painting. * Side walk
* Electrical. * Plumbing
* Wood Flooring; Tile Work
* Kitchen remodeling
* Bathroom remodeling
* Sheetrock. * Gutter Cleaning
* Fences
* Framing. * Brick Pointing
* Window replacement
* Build a project from scratch
Experience at both commercial and residential
Free Estimate.
Mike 917-968-6755 |
| Aa plus construction |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Job should always be based on material cost and how long it take to complete the project. |
| Usher & Miller Construction |
Answer: Time and materials (T&M) Explanation: In my experience most contractors will determine their bid by adding material cost to the amount of time it would take to complete the task. Nte stands for not to exceed, and is usually given to a tech or person handling the job as a limit set by someone that actually bidded the job. Fixed price for fixing metal work I believe leaves too much room for error because every job is different and may require a different approach than the last. |
| Rocky Mountain maintenance LTD |
Answer: Time and materials (T&M) Explanation: It all depends on the project |
| Project pros |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: The standard way to approach projects is with a fixed price bid. |
| Visionary General Contracting, LLC |
Answer: Time and materials (T&M) Explanation: PBI prefers the T&M method for residential work. The client can choose the material of choice such as fixtures and finishes and we will provide labor and equipment to complete the installation. This saves our clients alot of time and money than having someone bill hours of design services. |
| Penn Builders & Installations Co, Inc |
Answer: Time and materials (T&M) Explanation: Contractors like myself calculate the time a project will take and the cost of all materials involved to come up with a final price. |
| P.M.R Services LLC |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: Most customers are looking for hard bids for their projects. Many contractors prefer to bid jobs on a Time and Material basis because it protects them from contingencies and unexpected costs incurred during the project. |
| Cronin Construction & Resource Management, LLC |
Answer: Fixed price for a fixed amount of work Explanation: It is a certain amount per square with factors including but not limited to Pitch, layers of existing shingles, skylight installation, accessibility, numerous facets, etc. |
| Suburban Steel Roofs |
Answer: Fixed price for a fixed amount of work Explanation: We use a computer program designed to give current prices. |
| Awlpoints Reconstruction |
|
| ProMatcher |
Answer: Fixed price for a fixed amount of work Explanation: We give a quote for labor and material. |
| Home Inavations by Jones Construction |
Answer: Time and materials (T&M) Explanation: By adding the cost of materials and labor together and then putting a percentage on the end to cover company overhead and profit. |
| Ideal Construction L.L.C |
Answer: Fixed price for a fixed amount of work Explanation: We offer flat rate pricing or pricing per square feet for 95% of the jobs we complete. |
| Construct Boss |
|
| ProMatcher |
Answer: Time and materials (T&M) Explanation: Fixed bids mean contractors must add a "risk percentage" to the price to guarantee that they don't lose money on a project. A well managed time and materials plan will save most customers money. |
| McLaughlin Design & Construction LLC |
Answer: Time and materials (T&M) Explanation: I personally like the bid by the job, it keeps you motivated and allows scheduled time for quality work. |
| Property Repair Service & Inspections |
Answer: Price not to exceed (NTE) Explanation: Bid and don't go over that bid unless they ask for more services |
| Wagoner's Construction & Remodeling |
|
| ProMatcher |